DPW Updates

2014 Summer CIP Road Construction

Expand DPW Updates Menu [ + ]

Select a Department

2014 Summer CIP Road Construction

As part of the City's Capital Improvement Project for 2014, an estimated 38,000 ft of roads around the City of Hartford will be milled and paved during the Summer of 2014.

2014 Spring and Summer Paving Map (PDF)

 

Street Limits Milling Dates Paving Dates
Palm St Burnham to Lyme Completed Completed
Chatham Cornwall to Blue Hills Completed Completed
Sharon St Cornwall to Blue Hills Completed Completed
Edgewood St Greenfield to Garden Completed Completed
Magnolia St Greenfield to Albany Completed Completed
Cabot St Albany to Homestead on hold on hold
Kent St Homestead to Albany Completed Completed
Woodland St* Farmington to Asylum  Completed Completed 
Westerly Terr Albany to Albany Completed Completed
Terry Rd Westerly to Asylum Completed Completed
 Prospect Ave Farmington to Asylum Completed Completed
Henry St  Grandview to Roxbury Completed Completed
 Mountford St Broad to Maple Completed Completed
 Victoria Rd Franklin to George Completed  Completed
Hubson St * Capitol thru Pulaski Cir Completed  Completed
 Main St* Cleveland to Capen Completed  Completed
Jennings Rd* 100' W of Leibert to end Completed  Completed
Colt Park   775' Park Rd Completed   Completed 
830 Maple Ave Senior Center Completed Completed
Columbus Blvd* State St Intersection Completed Completed

 Note: Dates are subject to change due to inclement weather

*Means Night Paving

 

Click to Expand Menu [ + ]

Department of Public Works Contact

Department of Public Works
50 Jennings Rd
Hartford, CT 06120
Office: (860) 757-9900
Fax: (860) 722-6215

Office Hours:
8:00am - 5:00pm

HARTFORD CITY HALL ADDRESS: 550 Main Street, Hartford, CT 06103 PHONE: (860)757-9311 HOURS: 8AM - 5PM