2015 Spring CIP Road Construction

Expand DPW Updates Menu [ + ]

Select a Department

2015 Spring CIP Road Construction

2015 Spring Road Construction Map (PDF)

 

Street Limits Milling Dates Paving Dates
**Park St** Main to Park Terr Completed Completed
Garden Albany to Mathers Completed Completed
Mather Vine to Bedford Completed Completed
Enfield Mather to Capen Completed Completed
**Buckingham St** Main to Washington Completed Completed
Greenfield Ridgefield to Garden Completed Completed
Hebron Granby to Blue Hills Completed Completed
Chatham Lyme to Cornwall Completed Completed
Lyme Chatham to Plainfield Completed Completed
Cornwall Chatham to Hebron Completed Completed
Sharon Granby to Cornwall Completed Completed
 West Raymond Edgewood to Vine  Completed Completed
 East Raymond  Vine to Middlefield Completed Completed
 Middlefield  E Raymond to Greenfield Completed Completed
 Baltimore Albany to Norfolk  Completed Completed
 Woodside Cir All on-hold on-hold
Cone Prospect to Whitney Completed Delay
Prospect Ave Farmington to Warrenton Completed Completed
 West Bourne PKWY  Albany to Ridgefield Completed Completed
Adam Homestread to Albany Completed Completed
**No.Chapel & Walnut** Main to Garden Completed Completed
**Capitol** Forest to Laurel Completed Completed
**Washington** Capitol to Buckingham Completed Completed
**Lafayette** Capitol to Park Completed Completed
**Washington** Jefferson to New Britian Completed Completed
**Barnard** Maple to Washington Completed Completed
**New Britian** Hillside to Washington Completed Completed
**Zion** New Britian to Hamilton Completed Completed

 Note: Dates are subject to change due to inclement weather

**Means Night Paving

 

Click to Expand Menu [ + ]

Department of Public Works Contact

Department of Public Works
50 Jennings Rd
Hartford, CT 06120
Office: (860) 757-9900
Fax: (860) 722-6215

Office Hours:
8:00am - 5:00pm

HARTFORD CITY HALL ADDRESS: 550 Main Street, Hartford, CT 06103 PHONE: (860)757-9311 HOURS: 8AM - 5PM